Short-load concrete delivery in northern New Jersey

For a two-yard order, Short Load Concrete’s posted charges total $420–$490. Quick Stop’s figures give $590–$740, including fuel. Confirm the address, mix and minimum before choosing a supplier.

Supplier pages checked . Prices in US dollars.

What do one, two or three yards cost?

One weekday trip, before tax and optional fees
OrderedShort LoadQuick StopMinimix
1 yd³$305–$375$440–$590$342–$532
2 yd³$420–$490$590–$740$489–$679
3 yd³$535–$605$740–$890$636–$826

Read each column as one supplier’s range across its own delivery zones. Only Short Load Concrete publishes an order range that explicitly confirms all three quantities. The other two columns assume the supplier accepts that order on one trip.

Where the New Jersey charges come from

Short Load Concrete in Paterson and Bridgewater

For two yards, its listed 3000 LB mix costs 2 × $115 = $230. Add one truck charge of $190, $200, $220, $230 or $260. A dispatcher can assign the correct zone for your street. A card payment adds 3%. Orders above 3½ yards need another trip, and the supplier asks customers to call about the price of additional deliveries. Short Load prices · Truck limits and plant contacts

Quick Stop Ready Mix in Hawthorne

Its 3,000 PSI mix costs $150 per yard. Add one listed $45 fuel surcharge and the confirmed truck fee of $245, $285, $375 or $395. At two yards the material and fuel come to $345 before the zone charge. Confirm the order minimum and fuel charge with dispatch. Quick Stop prices

Minimix in Pequannock

Two yards of its 3,000 PSI mix with ⅜-inch stone cost $294. Small-truck zones add $195 to $385. Our example uses ⅜-inch stone because both of the supplier’s pages give that mix the same price. Specify the required aggregate and truck when requesting a comparison. Minimix truck fees · Mix list

Comparing two quotes for one street

Give each dispatcher the same address, quantity, strength, aggregate and delivery time. Ask for the subtotal with delivery and fuel, then confirm tax, card fees, unloading time and any repeat-trip charge. Zone numbers belong to individual suppliers. A street in one plant’s first zone can fall in another plant’s outer zone.

For metered pours in Paterson or small deliveries from Wayne, see the additional northern New Jersey concrete suppliers.